Thursday, May 25, 2017

week 36: final presentation

The Final presentation was overall successful. the 12th scaled team seemed to be doing a lot better than the half scale.

week 35: fixing the corners

The main failure happened during the Paseo Public Prototyping was that the bogie falling off from the corners. The whole team had been trying to solve this problem.The first idea was to add height to the corners so when the bogie tilts, it would have more surface area for the upper guide. The final solution was adding layers to the inner part of the corner so that the bogie would not tilt when it comes to the corners.

week 34: solar panel rack request update

The current main job is the request of solar panel rack from solar team. The progress is at about 20% according to Kevin.


The next task coming up is the final presentation at May 12th. The overall progress is on point.